Last update : 12th August 18th November 2023

There are two documents relevant to data previews and releases :

Rubin Observatory Plans for an Early Science Program (Leanne Guy et al. RTN-11), latest version is dated 4th 31st October 2023.

Release Scenarios for Rubin - LSST Commissioning and Survey Data” (Phil Marshall et al. RDO-11) latest version is dated 10th February 2023.

On 23rd November 2022, the project released an important update on the Construction Plan. On-sky data with ComCam will NOT be taken. It is anticipated that LSSTCam will now be ready to take on-sky data at the time when ComCam was due to do so (originally end of 2023, but likely now to be July 2024). The DP1 and DP2 plans have changed.This is generally good news as on-sky commissioning with ComCam will be replaced with on-sky commissioning with LSSTCamSignificant changes ….

Operations schedule : https://www.lsst.org/about/project-status

...