Guy et al. RTN-11 : summary

...

Useful definitions : (see the bottom of this page for the description of the data products in this Table 1 from Guy et al.).

System First Light : a milestone that marks the end of the on-sky engineering phase
System optimisation and Science Validation phase : period of about 4 months after System First Light
Start of LSST Science operations : projected about 4 months after System First Light and after the Science Validation phase has been successfully completed

...

Data release dates and observation coverage

There was is a revised full 10 year approximate data release schedule in Marshall et al. RDO-11, but since this has been superseded which is now aligned with the schedule outlined in Guy et al. , it has been removed from this page. The schedule from the new and updated version of RDO-11 (expected soon in 2023) will be summarised here when available. document.

...

Details of what will be included in the various data releases

As noted above DP1 and DP2 will be revised such that there will be no on-sky data with ComCam, and the project will move more quickly to LSSTCam on-sky data. A revised Marshall The Guy et al. document all above outlines what will be released in 2023. I have deleted the previous schedule which was posted here and we are awaiting a new version of RDO-11. the data releases and here is the Table 1 from Marshall et al. describing what those data products are.

...